It was a slow but very productive week. Details are still being worked out and a mockup will be installed shortly for the council to approve for the counter flashing n the chimney. We have approximately 1 ½ units complete this week and the production will be picking up next week as the crew has established work procedures for most areas now. Abney Roofing is expecting to add a few more workers early next week to increase the crew size.