The crew have begun work at unit 313. They have removed a portion of the roof and have installed new insulation baffles at each truss. The installation of new plywood is going well. Work on units 311 and 312 is almost wrapped up and installation of attic vent and wall flashing are being installed on the lower elevations and finishing work on the chimney counter flashes. The bin is going to be moved and re-positioned in front of units 309 and 310, this will be happening either today or early next week.