There has not been a lot of progress this week due to poor weather. However with that being said the crew did finish the shingling on Unit 403 this week. Unit 308 did not have much progress completed this week.
BC Roof Inspections has completed final inspections on 4 out of 5 units this week, with deficiencies being currently worked on by Abney Roofing.