Roofing Weekly Update

Again the crew has progressed well this week, by the end of today unit #405 will be 85% complete, and unit #306 will be 50% complete.

The telescopic forklift is now onsite and will be utilized by the crews from now on and we are hoping that we can speed up the process for these roofs and decrease the time to do each unit from 5 days down to 3.5 – 4 days. Plywood and garbage box have been consolidated into one location to free up another parking space.

Crew will be starting again early next week, weather permitting. Hope you all have a fantastic weekend.