The crews are moving along with the project despite the cooler temperatures. The gutters had begun being installed on Tuesday, and they are now 60% complete to the 300 block.
Slope roofing on the 300 block is 80% complete and should be finished in the next couple of weeks.
Flat roofing crew on the 400 block is 90% complete, with some minor details to still finish up before they head over to the 300 block to start the flat roof sections.