- Gutter crew will be back in Maples for Monday Jan 4, all remaining gutter work for completed roofs is likely to be completed that day
- Soffit vent project and remaining skylight tunnel carpentry is scheduled Monday Jan 4 thru Thursday Jan 7 and should also be completed by Thursday end
- All roof membrane and shingle assembly for all reroofed units should be completed including any noted deficiencies to be rectified, by Tuesday’s end
- Custom metal for flat roofs will be measured and ordered Monday Jan 4
- (6) flat roof vent lids with screens and (3) custom chase cap flashing are scheduled to be installed Monday and / or Tuesday
- Inside inspections required and perimeter check of all reroof units, gutter / fascia and drainage component checks Wed / Thursday
- Pull Porto toilet and storage fencing for Thursday
- Last of custom sheet metal to be installed once order is ready from sheet metal shop.