From BCRI:
The 400 block will be 92% complete by the end of the day with just a few minor details to be done by the beginning of next week. The crew will be starting at Unit 215 on Monday. Carpenters will be around on the 100 and 200 block to start installing the soffit air intake vents. The bin will be moved to the 200 block by the end of the day Tuesday and the pool is open to everybody as of tomorrow as it will be complete.