Roofing Progress Update

From BCRI:

Crew has made good progress on the 100 block. By end of today 60% of the 100 block will be nearly complete. The flat crew on the 200 block will be closely finished on the torch on application and flashing will be installed short way after being completed. The crew will be retuning early Tuesday to wrap up the slope sections of the 100 block before moving onto the 600 block.