From BCRI:
The crew has progressed well this week even with the shortened week due to the long weekend and inclement weather. The last slope portions of the roof will be completed by the end of next week weather permitting. And the flat roofs will be started shortly after that. The cut flashing will be started shortly on the 200 block of the Maples which will complete that block. Crew will be retuning early next week to continue work on the 100 block.