From BCRI:
The crew has made some progress even with the poor weather we gave been having. By the end of today the 600 block will 65% complete on the slope elevations. The crew will be in tomorrow to finish up details on sections of the roof that were previously done gutter installation on the 200 block has started this week and 50% is completed to date, with the remainder to be completed by the end of next week. Soffit strip installation on the 100 block is 65% complete.
Flashing installer will be in also on Saturday to begin work on the 200 block. All crews will be returning early next week.
Note that a small roofing crew will be out on Saturday starting between 9 and 10am to do metal work in the 200’s.