From BCRI:
The crew have made progress this week with the shingles being 75% installed on the upper elevations. Used soffit strip installation have been completed on the 200 as well as the 100 block. Gutters are 95% complete on the 200 block, and started on the 100 block as they could not finish the 200 block because of arborists. The shingle and gutter crew will be retuning early next week to finish up where they left off. [The flat roof crew is] expected to start on the 100 block in 2 weeks’ time.
Interior repairs for leaks are expected to be completed in the next 1-2 weeks.