Roofing Progress Update

From BCRI:

The 600 block has progressed well with 85% of slope roofing complete. This should be finished up by early next week with commencement of the 500 block starting shortly after. The gutters on the 200 block are expecting to be completed by the end of the day on Monday, as well as the soffit work on the 100 block. The flat roofing will be commencing soon, starting on the 100 block and then moving to the 600 block, and lastly the 500 block.