Roofing Progress Update

From BCRI:

The slope roofs are nearing completion on the 600 block with the crew moving to the 500 block early next week. The crew is working on lower back roofs and minor deficiencies at this time. Gutters are now complete to the 200 block and we will be having the flat crew in late next week to start on the flat roofs on the 100’s, then move to the 600’s, and then wrap up at the 500’s. We have our fingers crossed that October will bring us lots of sunshine like September.

img_5069 img_5073