From BCRI:

A full crew is on site today for slope and flat elevations, with the flat crew starting on the 100 block, and the slope crew continuing on the 500 block. The slope crew is planning on coming in tomorrow weather pending to continue work, but due to the uncertainty of the weather the flat crew will not be. Weather pending, both crews will return to site next week to continue working. The drywall finishing carpenters have also been on site finishing work inside the skylight tunnels.

image1 img_8065 img_8079