Roofing Progress Update

From BCRI:

The crew has made headway despite the past months rainfall. Just over 1/3 of the 500 block have now received laminated asphalt shingles, and 3 / 4 flat roofs on the 100 block have been completed, as well as the gutters and downpipes. The gutter installers will be starting the 600 block shortly, the crews have will not be working this weekend due to weather concerns.