Roofing Progress Update

From BCRI:

The crews have made some progress again this week. They are moving forward on the slope sections of the 500 block. By the end of today the crews will be half way done on the slope sections. The flat roof sections have almost been completed on the 100 block. Once the crew is complete on the 100 block the crew will move to the 600 block. This is anticipated to be sometime next week weather permitting. The gutters are expected to start in the 600 block as well at that time.

img_9333 img_9336 img_9342