Roofing Progress Update

From BCRI:

Despite the very poor and wet fall we have been encountering, the crew is moving forward very slowly, but surely. We have approximately 5 days left of the slope roofs plus outstanding deficiencies to be corrected and the flat roofs have approximately 10 days until all flat roofs are completed. The crew has been working under tarps and making slow progress due to the weather. Gutters on the 600 block have 2 more days and then they will be completed. We are hoping to have all roofing complete by the end of the second week of December with deficiencies and gutters being completed in the following weeks.