Roofing Progress Update

From BCRI:

The crew has completed the majority of the slope roof sections, the flat roof sections will be started [next week], weather permitting. The crew will be starting early next week on the 100 block, starting at the far end and working towards the flat roof sections. The final details, gutters, and carpentry work still to be completed on the 200 block will be completed in the next few weeks.

Please note:
The flat roofing materials are being delivered to site Monday mid-morning, reroofing of flat roofs is scheduled for Tuesday or Wednesday, weather will need to be almost perfect for flat reroofing.