Roofing Progress Update

From BCRI:

By the end of the day today 25% of the 600 block will be done with the slope roof section. Remaining details on the 200 & 100 block have been worked on and wrapped up today and early next week. The gutter crew should be on site as early as Wed next week to start work on the gutter replacement.

IMG_0757 IMG_0750