From BCRI:
The crew have made good head way on the project this week. Painting on the 100 block is 80% complete with the flat roofing estimated to begin in 2 weeks time. The ventilation soffit strip is near complete on the 200 block which will be completed shortly.
Gutter replacement will be starting shortly on the 200 block as well. By the end of the day 50% of the upper roofs will be completed on the 200 block. The crew will be returning early next week to continue work.
If you have any concern please do not hesitate to contact us and we will see you next week.